This page contains a list of scheduled project events, and key milestones and deliverables. In addition, we maintain the following prioritized lists of what we're working on this week, and what we plan to do next week: Week 11/11/2002
Week 11/18/2002
Week 11/26/2002
Back to TopMilestones and DeliverablesOctober 28, 2002 -- Project proposal due
November 6, 2002 -- Status report due
November 10, 2002 -- Achieved frequency setting on the iPAQ.
November 18, 2002 -- Status report 2 due
December 2, 2002 -- Status report 3 due